Chandos Construction Ltd v Associated Engineering Alberta Ltd, 2026 ABCA 376
How does the test for summary dismissal apply to applications on the basis of an expired limitation period, and when do the limitations periods for claims on a construction project start to run? The Alberta Court of Appeal addressed these issues in its decision in Chandos Construction Ltd v Associated Engineering Alberta Ltd, 2026 ABCA 376.
Associated Engineering Alberta Ltd (“Associated Engineering”) and the Municipal District of Greenview No. 16 (the “Municipal District”) appealed the decision of a chambers judge dismissing their application for summary dismissal of claims for delay and additional work on a construction project. A majority of the Court of Appeal allowed the appeal and granted partial summary dismissal of the claims of Chandos Construction Ltd. (“Chandos”).
The Facts
In 2015, the Municipal District and Chandos entered into a fixed price agreement for construction of a new water treatment plant and upgrades to existing water infrastructure. Associated Engineering designed and administered the project on the Municipal District’s behalf. The construction agreement contemplated that the work would be completed by March 2017; however, there were issues and Chandos did not issue its final certificate of substantial performance until September 2018.
Chandos issued multiple notice letters to the Municipal District and Associated Engineering between May 2016 and June 2018. Fourteen notices purported to provide “notice of delay” or “potential impact”, and many of them advised that Chandos was incurring costs. Despite that, the notices did not include any claim for payment.
In December 2018, Chandos issued a letter to Associated Engineering requesting a 17-month extension of the contract time and an increase in the contract price on account of delay.
Ultimately, Chandos filed a statement of claim in September 2020, alleging damages associated with delay and “additional work”. The delay claim related to the matters addressed in the fourteen delay notice letters.
The Municipal District and Associated Engineering applied for summary dismissal of Chandos’ claim. Initially, the application related only to dismissal of the delay claim on the basis of the Limitations Act; however, the application was subsequently amended to include the additional work claim.
In response to the application, Chandos filed an affidavit of its project director. The affidavit stated that the notice letters did not demand compensation but provided notice of a potential claim. It asserted that Chandos could only review the impacts of the events in the notice letters after substantial completion, and that is would have been uneconomical and impractical for Chandos to have considered initiating multiple court proceedings for each instance.
The summary dismissal application was dismissed before the applications judge and chambers judge. Associated Engineering and the Municipal District (together, the “Appellants”) appealed to the Alberta Court of Appeal, arguing that the chambers judge applied the wrong test for summary dismissal and that the claim of Chandos (the “Respondent”) was barred under the Limitations Act and by terms of the construction agreement.
The Court of Appeal Decision
The Majority Decision
Justice Antonio and Justice Friesen allowed the appeal and granted the Appellants’ application for summary dismissal of the Respondent’s delay and additional work claims.
The majority agreed with the Appellants in finding that the chambers judge erred in applying too high a standard to assessing whether summary judgment was appropriate, clarifying that applications for summary dismissal are not subject to special treatment or different standards because they are based on limitations grounds.
The majority then considered the Appellants’ underlying summary dismissal application. The Appellants sought summary dismissal on the basis that Chandos’ claims were brought after expiry of the limitation period.
The Appellants’ limitations defence was grounded in section 3(1)(a) of the Limitations Act. Section 3(1)(a) provides that a defendant is entitled to immunity from liability relating to a claim if the claimant does not seek a remedial order within two years after the date on which the claimant first knew, or in the circumstances ought to have known:
(i) that the injury for which the claimant seeks a remedial order had occurred,
(ii) that the injury was attributable to conduct of the defendant, and
(iii) that the injury, assuming liability on the part of the defendant, warrants bringing a proceeding.
The parties disagreed on the first and third requirements under section 3(1)(a).
On the first requirement – knowledge that an injury had occurred – the Appellants relied on the fact that for each claim, the respondent performed the additional work or incurred the associated delay prior to July 11, 2018. The Appellants argued that the respondent was accordingly aware it had sustained economic loss, and therefore an “injury” for purposes of the Limitations Act before that date.
On the third requirement – that the injury warranted bringing a proceeding – the Appellants relied on the admissions of the Respondent’s representative that it was tracking costs and delay during the course of the construction work and that the notice letters were issued because the events noted in the letters were “causing something more than a trivial cost or impact upon Chandos”.
The Respondent made three main arguments in response, all of which were rejected by the majority:
First, the Respondent argued it did not know an injury had occurred or that it warranted bringing a proceeding because it did not know the magnitude of the costs attributable to the additional work and delay claims until the end of the project. The majority stated that a plaintiff does not need to know the exact extent or type of harm it has suffered, or precise cause of its injury, in order for the limitation period to run. Citing the evidence of the Respondent’s representative and the notice letters, the majority stated that the Respondent’s pursuit of precise quantification did not remove its existing awareness that it had sustained a significant cost impact in respect of the additional work and delay claims prior to July 11, 2018.
Second, the Respondent argued it would have been uneconomical and impractical to consider initiating multiple instances of court proceedings relating to the project. The majority stated the discoverability-based limitation begins to run when a claimant has actual or constructive knowledge that it has sustained an injury attributable to the conduct of the defendant that warrants a proceeding. This does not require a claimant to seek a remedial order at that time.
Third, the Respondent argued it was not aware that an injury had occurred or that it warranted bringing a proceeding until the Appellants refused to pay, particularly if the parties were negotiating in the meantime. The majority rejected this position as untenable, stating that it would undermine the traditional certainty, evidentiary, and diligence rationales that underpin limitations legislation. It recognized that in some cases a refusal to pay will trigger the start of a limitation period, such as payment of an invoice; however, non-payment of a previously agreed obligation to pay was not alleged in the claims in this case. The alleged wrongful conduct in the Respondent’s claim occurred before the related costs were incurred and there was no certainty these costs would be repaid. The majority further rejected the Respondent’s argument that negotiation suspends the limitation period. It noted the case law is clear that ongoing settlement communications, investigations, or negotiations do not, on their own, postpone the commencement of a limitation period.
The majority concluded that for each relevant claim, the Respondent was aware of the alleged wrongful conduct on the part of the Appellants and that it had suffered a significant cost impact as a result of that conduct before July 11, 2018. The majority further found that the Respondent knew before that date that the cost impact, and the potentially recoverable damages, far exceeded any trivial, minimal, or speculative amount, meaning that it was aware that its injuries were sufficiently serious to warrant bringing a proceeding. Accordingly, the majority found that the requirements of section 3(1)(a) of the Limitations Act were met and that the respondents were entitled to the limitations defence.
The majority left open the possibility that compliance with an alternative contractual claims process could delay the running of a limitation period, but found that there was no basis on which to find that was the case in this circumstance.
As a final point, the majority stated that the suggestion of policy arguments specific to the construction context or evidence of such considerations might later be adduced is not enough to resist summary dismissal, relying upon the principal of best foot forward.
The Dissent
While agreeing with the majority that the chambers judge applied the wrong test for summary dismissal, Justice Feth in a dissenting opinion would have only summarily dismissed a portion of the additional work claim, but denied the summary dismissal application on the remaining claims.
Key Takeaways and Considerations Regarding Applications for Summary Dismissal and Limitations Periods
The Court of Appeal’s majority decision in Chandos Construction Ltd v Associated Engineering Alberta Ltd offers clarity and points for consideration regarding applications for summary dismissal and limitations periods arising on construction projects and claims more generally.
The majority reviewed the law applicable to applications for summary dismissal, noting that the general principles relating applications for summary judgment under Rule 7.3 of the Alberta Rules of Court also apply to those under Rule 7.2(a). The Court clarified that applications for summary dismissal on grounds of an expired limitation period are not subject to a higher standard or special treatment. The usual summary judgment principles apply.
The majority particularly noted that a party cannot resist a summary dismissal application merely by identifying potential arguments or evidence which could be developed at a trial. Any genuine issue for trial must be grounded in the evidentiary record.
In considering the limitations issue, the majority offered clarity on how the knowledge requirements under section 3(1)(a) of the Limitations Act may apply, particularly knowledge that an injury had occurred, and that it warrants bringing a proceeding. The application of the Limitations Act will be specific to the circumstances of each case. For example, the nature of the claims and wrongful conduct alleged were important factors in the majority’s decision. However, the decision indicates that in appropriate circumstances a limitation period can start to run even before a demand for payment is made and that a precise quantification of damages is not required for a claimant to have the threshold knowledge that a claim warrants bringing a proceeding.
When events occur that may give rise to a claim, parties should consider the relevant considerations for a defence under the Limitations Act and assess when the limitation period may start to run. This is important both to parties that consider bringing a claim as well as potential defendants that may seek to raise a defence if the relevant limitations period expires. Contractors should assume a limitation period starts to run at the time an issue occurs, rather than relying upon completion of the project, final quantification of claims, submission of a formal demand, exhaustion of negotiation, or rejection of the claims.
This post is meant to provide information only and is not intended to provide legal advice. Although every effort has been made to provide current and accurate information, changes to the law may cause the information in this post to be outdated.